Monday, April 11, 2011
the past 2 weeks
the past 2 weeks we have put down floor insulation and fixed it therethen we sqweared up the floor boards and and nailed them in 150mm appart on the out side and 200mm appart nailing it 2 the floor joist. We have also got the back wall up we had 2 put some stops so it didnt slide of the back. Once we have put it were it is going to be we nailed tacks down and got a brace and made sure it was strate up with the leveler.We had 2 do the same drill will all of the walls. once all the walls were fixed down with the braces we string lined the end of the walls to make sure they were strate and the top if it was to hight we would have 2 put a smaller nog in. On monday we started on the roof